Harvey Senior Citizens Centre Expansion

Project overview

With over 300 current members, the Harvey Senior Citizens Centre offers a range of social and well-being activities every week.

However, with a growing proportion of seniors living in Harvey, the Centre is experiencing an increase in the demand for services and is unable to cater for this potential growth in its membership base. The expansion project will see the addition of a brand new social area, office space, accessible toilets and facade upgrades.

In July 2020, the Shire prioritised the upgrade of the Centre will Council allocating $125,000 towards the project.

As a key project of the Shire's Advocacy Priorities 2020 - 2021, the expansion received a further $610,000 from the Government of Western Australia(External link).

Construction is curently underway, with an expected completion date in October 2024. 

Project timeline

  • August 2022 - Geotechnical and compliance testing, feature survey and site measure complete. 
  • September 2022 to March 2023 - Design development.
  • March 2023 to July 2023 - Contract documentation. 
  • July 2023 - Development Application Approved.
  • January 2024 - Tender awarded to Hoskins Investments Pty Ltd
  • April 2024 - Construction commenced at Harvey Senior Citizens Centre 
  • November 2024 - Expected completion of building works