Prohibited Burning Period until midnight 14 March 2025

All burning is prohibited during this period. For up to date information regarding Total Fire Bans and community warnings about emergencies, visit Emergency WA.

Close alert

Australind Jetty Update

Australind Jetty Update
16 May 2023

The Australind Jetty Project - Stage 1 is estimated to be completed in mid-June.

Works are progressing on the Australind Jetty Project - Stage 1.

Crews have entirely removed the existing boardwalk decking and stringers.

Approximately 95 per cent of the new stringers have been installed and the boardwalk headstock and pile bolts have been entirely replaced. 

Temporary fencing at the boardwalk entrance has been removed and additional temporary site fencing around the forecourt area has been installed.

Timber from the old jetty has been salvaged. When Stage 1 works are completed, reclaimed timber will be distributed to the Shire of Harvey, Leschenault Men's Shed, Brunswick Junction Men's Shed and Eaton Primary School.

Meanwhile, the remaining long stringer beams will be sold to Yallingup Post and Beam.

For more information, visit the WA Government website.